Stucco'n You!
Who knew Lionel Richie sang a song about Stucco?
January 10, 2019
Our third trip to Floor and Decor, we went ahead and purchased the tile so that we wouldn't run the risk of it being out of stock. We will have it delivered to the house when the installers are ready.
January 11, 2019
The plumbing was finished and testing was done. Knapp Stucco company dropped off scaffolding.
January 16, 2019
Scaffolding was set up and preparation for applying stucco to the parapet walls began.
January 18, 2019
A styrofoam layer was applied to the top of the parapet walls.
January 19, 2019
The exterior of the concrete blocks of the parapet wall and garage level were prepared for stucco.
January 20, 2019
We chose the colors for the exterior. The house will be "Greek Villa" white. The garage doors and window trim will match the dome, "Blue Chip".
January 23, 2019
Stucco supplies were delivered.
January 29, 2019
First coat of stucco was applied to the parapet walls.
February 1, 2019
Two workers began the process of applying stucco to the house. It went very slowly.
February 3, 2019
More stucco...
They applied styrofoam forms around the windows for the trim that will be painted blue to match the dome.
February 5, 2019
More stucco...
February 6, 2019
More stucco...
February 7, 2019
More stucco guys showed up and the job went faster! They repaired some imperfections in the underside of the upper deck and applied more stucco to the north side of the house.
February 8, 2019
The workers began to apply the first stucco coat to the back of the house.
February 11, 2019
The stucco was applied to the elevator shaft.
Work continued on the back of the house.
February 12, 2019
First coat of stucco is complete!
February 15, 2019
The insulation company came to apply the spray foam insulation on the ceiling of the garage and the ceiling of the 3rd floor. We were concerned about the amount of insulation on the 3rd floor so Tony asked the builder to have them come back out and apply more.
They also sprayed insulation in all of the channels where the plumbing and electrical wires are.
They sprayed insulation in the opening where the cooktop vent will go.
Third floor ceiling insulation
February 19, 2019
The sheetrock has been delivered!
We met with the builder to discuss placement of the buried propane tank. The tank has to be at least 10 feet from the house and 10 feet from the property line. We have barely enough space for the tank. He proposed that we put it between the middle garage door and the front entrance, buried in an island with brick pavers around it.
We discussed the project schedule. He thinks the drywall will begin tomorrow and should be complete by the end of next week. The tile team is on deck and expect to begin tiling as soon as the sheetrock is done. The cabinets have arrived and will follow the tile installation. The city is requiring us to plant 6 palm trees so we need to get that scheduled.
This is starting to seem real! We might actually have a house one of these days!
Stay tuned!
January 10, 2019
Our third trip to Floor and Decor, we went ahead and purchased the tile so that we wouldn't run the risk of it being out of stock. We will have it delivered to the house when the installers are ready.
January 11, 2019
The plumbing was finished and testing was done. Knapp Stucco company dropped off scaffolding.
January 16, 2019
Scaffolding was set up and preparation for applying stucco to the parapet walls began.
January 18, 2019
A styrofoam layer was applied to the top of the parapet walls.
January 19, 2019
The exterior of the concrete blocks of the parapet wall and garage level were prepared for stucco.
January 20, 2019
We chose the colors for the exterior. The house will be "Greek Villa" white. The garage doors and window trim will match the dome, "Blue Chip".
January 23, 2019
Stucco supplies were delivered.
January 29, 2019
First coat of stucco was applied to the parapet walls.
February 1, 2019
Two workers began the process of applying stucco to the house. It went very slowly.
February 3, 2019
More stucco...
February 5, 2019
More stucco...
February 6, 2019
More stucco...
February 7, 2019
More stucco guys showed up and the job went faster! They repaired some imperfections in the underside of the upper deck and applied more stucco to the north side of the house.
February 8, 2019
The workers began to apply the first stucco coat to the back of the house.
February 11, 2019
The stucco was applied to the elevator shaft.
Work continued on the back of the house.
February 12, 2019
First coat of stucco is complete!
February 15, 2019
The insulation company came to apply the spray foam insulation on the ceiling of the garage and the ceiling of the 3rd floor. We were concerned about the amount of insulation on the 3rd floor so Tony asked the builder to have them come back out and apply more.
They also sprayed insulation in all of the channels where the plumbing and electrical wires are.
They sprayed insulation in the opening where the cooktop vent will go.
Third floor ceiling insulation
February 19, 2019
The sheetrock has been delivered!
We met with the builder to discuss placement of the buried propane tank. The tank has to be at least 10 feet from the house and 10 feet from the property line. We have barely enough space for the tank. He proposed that we put it between the middle garage door and the front entrance, buried in an island with brick pavers around it.
We discussed the project schedule. He thinks the drywall will begin tomorrow and should be complete by the end of next week. The tile team is on deck and expect to begin tiling as soon as the sheetrock is done. The cabinets have arrived and will follow the tile installation. The city is requiring us to plant 6 palm trees so we need to get that scheduled.
This is starting to seem real! We might actually have a house one of these days!
Stay tuned!