Good Looking Studs!

It seems like the structure is now complete so the workers are concentrating on framing the interior. September 11, 2018 Pouring the concrete for the parapet walls and elevator shaft. September 12, 2018 We learned that when they were pouring the elevator shaft, they noticed the sides were bowing with the weight of the concrete so they had to stop the pour and put up some braces to shore up the styrofoam forms. It was time to order the dome for the elevator shaft which meant it was time to pick the color that would be integrated into the fiberglass. We want it to look like a house in Santorini, Greece but it is really hard to tell anything from these little swatches! These two pictures are the same two swatches in different lighting situations. We chose "Blue Chip" - the one on the right. September 13, 2018 The 2nd floor cantilevered deck with the supports removed. There will be stainless steel wire rail...